Code · CFR · Title 18 — Conservation of Power and Water Resources · Part 5 — Integrated License Application Process · § 5.22

§ 5.22. Notice of acceptance and ready for environmental analysis.

288 words·~1 min read·/us/cfr/t18/s§ 5.22·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)When the Commission has determined that the application meets the Commission's requirements as specified in §§ 5.18 and 5.19, the approved studies have been completed, any deficiencies in the application have been cured, and no other additional information is needed, it will issue public notice as required in the Federal Power Act:
(1)Accepting the application for filing and specifying the date upon which the application was accepted for filing (which will be the application filing date if the Secretary receives all of the information and documents necessary to conform to the requirements of §§ 5.1 through 5.21, as applicable, within the time frame prescribed in § 5.20 or § 5.21);
(2)Finding that the application is ready for environmental analysis;
(3)Requesting comments, protests, and interventions;
(4)Requesting recommendations, preliminary terms and conditions, and preliminary fishway prescriptions, including all supporting documentation; and
(5)Establishing the date for final amendments to applications for new or subsequent licenses; and
(6)Updating the schedule issued with the tendering notice for processing the application.
(b)If the project affects lands of the United States, the Commission will notify the appropriate Federal office of the application and the specific lands affected, pursuant to Section 24 of the Federal Power Act.
(c)For an application for a license seeking benefits under Section 210 of the Public Utility Regulatory Policies Act of 1978, as amended, for a project that would be located at a new dam or diversion, the Applicant must serve the public notice issued under paragraph (a)(1) of this Section to interested agencies at the time the applicant is notified that the application is accepted for filing. \[Order 2002, 68 FR 51121, Aug. 25, 2003; 68 FR 61743, Oct. 30, 2003\]
Connections12 cite this
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.